(Created page with "== 3/18/11 == This Week Bullet point summary of key accomplishments over the past week. Next Week Goals for next week. Risks and Is...")
 
(3/18/11)
Line 1: Line 1:
 
== 3/18/11 ==
 
== 3/18/11 ==
 +
This Week:
 +
* Achieved photodiode signal with new fiber optic setup
  
      This Week
+
Next Week:
 +
* research and order parts needed for heated lid
 +
* figure out why the sginal amplification is so low
 +
* verify optical setup with mock system (blue LED + ND filter)
  
            Bullet point summary of key accomplishments over the past week.
+
Risks and Issues:
 
+
*
      Next Week
+
 
+
            Goals for next week.
+
 
+
      Risks and Issues
+
 
+
            List issues that may impact your project.
+

Revision as of 21:06, 18 March 2011

3/18/11

This Week:

  • Achieved photodiode signal with new fiber optic setup

Next Week:

  • research and order parts needed for heated lid
  • figure out why the sginal amplification is so low
  • verify optical setup with mock system (blue LED + ND filter)

Risks and Issues: